Construction Project Update
The upcoming construction work will include:
- Finishing up work on the standing seam roof over the admin wing and along the music staff area in the music library
- Finishing up masonry work
- More interior wall framing
The noise is not expected to be any different than it has during the past week.
The Latest Picture from the Tower Cam
Continuity Group Work Ahead
The Continuity Group is beginning to think about all the work that it will take to get the full staff into that part of the building you are looking at in the picture above. Everything from a timeline to the backup plans need to be developed for that transition to take place in March. Here are a few examples of issues we are starting to map out ...
How will VPR Classical work during the move of the CD library?
What will the sequencing be for moving everybody into the new space?
How will we book upcoming live performances without knowing studios availability?
How will the technology readiness be sequenced?